| TABLE: 4.7 POST TSUNAMI RECONSTRUCTION AND REHABILITATION PROGRAME | |||||||
| Atoll and Island | Number of housing units | Contract Sign Date | Expected End Date | Cost (Mrf) | Status | Financial Source (s) | |
| L.Maabaidhoo | 45 | 19-Mar-09 | 30-May-11 | 29,034,498 | Completed and handed over to beneficiaries | IDB Loan Assistance | |
| Th.Madifushi | 78 | 19-Mar-09 | 30-Sep-12 | 49,938,694 | 100% completed, to be handed over | IDB Loan Assistance | |
| 42 | 1-Feb-11 | 1-Feb-13 | 24,159,114 | Approx 20% | Abu Dhabi Fund for Development (ADFD) | ||
| M.Kolhufushi | 167 | 26-Jul-10 | 31-Dec-12 | 94,634,119 | Approx 80% | Abu Dhabi Fund for Development (ADFD) | |
| Ga. Villingilli | 77 | 20-Oct-08 | 28-Feb-13 | 220,460,096 | approx 64% | Saudi Fund | |
| Ga.Maamendhoo | 84 | 20-Oct-08 | 28-Feb-13 | Saudi Fund | |||
| Ga.Nilandhoo | 50 | 20-Oct-08 | 28-Feb-13 | Saudi Fund | |||
| Ga.Dhaandhoo | 87 | 20-Oct-08 | 28-Feb-13 | Saudi Fund | |||
| Source: National Disaster Management Center | |||||||